Servicing Rockhampton & surrounds · Free measure & quote · Enquire online ·  Tap to call
Sizing guide · Rockhampton, Gracemere, Yeppoon

How much concrete you need in Rockhampton: 1m³ covers 10m² at 100mm

Multiply length by width to get your area in m², multiply that by the thickness in metres, then add 5 to 15 per cent for wastage. A 45m² driveway at 100mm is 4.5m³ plus allowance, so you order 5m³. At $300 to $400 per m³ delivered for 25 MPa in the Rockhampton area, that is $1,500 to $2,000 of mix. Use the estimator below to size and price the concrete for your own job.

Concrete quantity and supply estimator

This sizes the concrete itself and prices the mix delivered to your gate. It is deliberately not a finished job price: labour, formwork, steel, finishing and curing are on the pricing page and in the concreting cost guide.

A double driveway is usually 40 to 60m². A 6m by 9m shed slab is 54m². A single car space is about 15 to 18m².
Add to the order
Estimated concrete supply, delivered $1,500 - $2,000

Mix delivered only. Indicative 2026 Rockhampton region rates. Send the quote form below for a fixed price on the finished slab after a site measure.

What this estimate assumes

  • Volume is worked from your area at the thickness you pick, then multiplied by the wastage allowance. It does not read your ground for you.
  • Supply rates are based on roughly $300 to $400 per m³ delivered for 25 MPa in the Rockhampton region, with 32 MPa and 40 MPa priced up from there.
  • It prices the mix only. Formwork, steel, bar chairs, membrane, labour, finishing, joint cutting and curing are not in it.
  • The thickened edge beam allowance assumes a normal residential perimeter beam. A designed beam on an H1 or H2 site uses more.
  • Batch plants usually sell in 0.1 or 0.2m³ steps and a standard agitator carries about 6 to 8m³, so a big slab is more than one truck.
  • We do not sell concrete by the metre. If you are pouring it yourself, order direct from a batch plant with the numbers you get here.

How to measure it properly with a tape and a phone

Ninety per cent of the ordering mistakes we see are measuring mistakes, not maths mistakes. Twenty minutes with a tape saves the argument at the chute.

  1. Measure in metres to two decimal places. Write 8.65, not “about eight and a half”. On a 4 metre wide driveway, 150mm of sloppiness at each end is most of a cubic metre.
  2. Measure both ends and the middle. Driveways and old slabs are almost never parallel. Use the average of the three widths, and if the difference is more than about 200mm, split the job into two rectangles instead.
  3. Break odd shapes into rectangles and triangles. Rectangle is length times width. Triangle is base times height divided by two. Add them up. A curve gets treated as the rectangle that contains it, which is deliberately generous, and generous is the right direction to be wrong in.
  4. Check the depth in three places, not one. Dig a test hole at each end and one in the middle, run a string line at the finished level, and measure down. The pad that looks flat is usually 20 to 40mm out somewhere.
  5. Photograph the tape. Lay the tape out, photograph each measurement with the numbers readable, and put the photos in one album. When somebody asks how wide the driveway was, you will have it.
  6. Allow for the fall. A driveway falling 1 in 100 across 4 metres is 40mm of extra depth at the high side if you are pouring to a level finish over a level base. Small, but it is real concrete.

The rules of thumb worth memorising

  • 1m³ covers 10m² at 100mm. Also 8m² at 125mm, 6.7m² at 150mm, 5m² at 200mm.
  • Every extra 25mm of depth on 50m² is 1.25m³, which is $375 to $500 of extra mix.
  • Wastage: 5 per cent formed tight and level, 10 per cent normal, 15 per cent on soft or uneven ground.
  • A 300mm by 300mm thickened edge beam adds about 0.06m³ per lineal metre over and above a 100mm slab, so 30 metres of perimeter is another 1.8m³.
  • Mesh: one SL72 or SL82 sheet per 13m² after laps, plus about 4 bar chairs per m².
  • Road base: order about 25 per cent more loose volume than the compacted depth you want.
  • Bagged premix: about 100 bags of 20kg per cubic metre. Only sensible under about 0.3m³.

The sizing mistake that costs the most here

It is not area, it is depth. Area is easy: you can measure it, and if you get it wrong by a metre you can see the mistake. Depth is invisible once the base is in, and a pad that finished 30mm low across a 60m² slab quietly swallows an extra 1.8m³, which is $540 to $720 of concrete nobody ordered. You do not discover it until the last truck is empty and the slab is not full.

That moment is worse than the money. If the pour stops for an hour while another load is batched and driven out from town, the concrete already placed has started to set, and where the new load meets it you get a cold joint: a permanent line of weakness through the slab that no amount of finishing will fix. In February heat that window is shorter again, which is why a summer pour needs its order to be right the first time. Our guide to the best time of year to pour concrete in Rockhampton covers the temperature side of that.

So over order slightly, always. Leftover concrete is easy to place: a bin pad, a step, an air conditioner base, a path to the clothesline, or a mower ramp at the shed door. Have one of those pegged out and ready before pour day and the surplus becomes something useful instead of a wheelbarrow of waste going back on the truck.

Rather have someone else do the measuring?

We measure for free anywhere from Parkhurst to Yeppoon, and the numbers come back to you as a fixed written quote, not an estimate.

Worked example: a 6m by 9m shed slab at Parkhurst

This is the most common slab we quote in the region, so here is the whole calculation with the numbers added up.

ItemWorkingQuantity2026 cost
Slab area 6.0m by 9.0m 54m² -
Concrete, slab at 100mm 54 × 0.10 5.40m³ -
Concrete, 300mm by 300mm edge beam 30m perimeter × 0.06 1.80m³ -
Wastage at 10 per cent 7.20 × 0.10 0.72m³ -
Concrete to order Rounded up to the next 0.2 8.0m³ $2,400 - $3,200
SL72 mesh 54 ÷ 13, rounded up 5 sheets $475 - $700
Bar chairs 4 per m², rounded up 250 $70 - $130
Road base, 100mm compacted 5.4m³ compacted, plus 25 per cent 7m³ loose $420 - $770
Materials subtotal Mix, steel, chairs and base - $3,365 - $4,800
Finished slab, placed and cured Materials plus excavation, formwork, labour, finish and curing - $7,500 - $9,500

The gap between the materials subtotal and the finished price is the part people underestimate: it is a crew, plant, formwork, a full day of finishing and a seven day cure. The tier by tier version of that number is on the budget shed slab page.

What to say when you order the mix

If you are ordering direct from a batch plant, they will ask for six things. Have them ready and the delivery goes smoothly.

  1. Volume in cubic metres, including your wastage allowance.
  2. Strength in MPa. 25 MPa for standard residential here, 32 MPa near the coast, 40 MPa for heavy duty or where you need early strength.
  3. Slump, which is how wet the mix is. Around 80mm is normal for a slab placed by hand, and a pumped mix is usually wetter. Do not order it wetter than you need.
  4. Aggregate size, normally 20mm for a slab and 10mm for thin sections and around dense steel.
  5. Additives, which in a Rockhampton summer usually means a retarder so the mix does not go off before it is finished.
  6. Delivery time and spacing if you need more than one truck, so loads arrive as you are ready rather than all at once.

One rule above all of those: do not let anyone add water at the chute to make the mix easier to spread. Extra water increases shrinkage and reduces the final strength, and it is the reason a slab that looked perfect on the day dusts and crazes six months later. Any water added on site is recorded on the delivery docket, which is why you keep the docket. Our warranty page explains why that one piece of paper matters more than any other if there is ever a strength argument.

When you should not be ordering concrete at all

Three honest cases. First, if the job is under about 0.3m³, which is a clothesline footing, a small step or a couple of fence posts, bags from the hardware store beat a truck once you account for the short load fee. Second, if the slab is structural, on reactive black soil, or is going to carry a house, a shed or a vehicle, the quantity is the easy part and the design is the part that matters: get the soil test and the engineered detail first, because ordering the right amount of the wrong specification helps nobody. Our page on slab prep on reactive soil explains what changes.

Third, if you are pricing this because you are thinking about placing it yourself: a driveway or a shed slab is not a first concrete job. You have one window, it is measured in hours, and in a Central Queensland summer it is shorter than you think. If you are doing it anyway, get help, start at first light, and read the day by day breakdown of a driveway job so you know what you are taking on. If you would rather it was our problem, the driveway surface guide is the next thing to read, and the form below gets you a fixed price.

Concrete quantity questions

How many square metres does a cubic metre of concrete cover?
One cubic metre covers 10 square metres at 100mm thick, 8 square metres at 125mm and about 6.7 square metres at 150mm. So a 45 square metre driveway at 100mm needs 4.5 cubic metres before wastage, and about 5 cubic metres once you add a 10 per cent allowance. Delivered in the Rockhampton area that mix costs roughly $300 to $400 per cubic metre for 25 MPa.
How much wastage should I allow when ordering concrete?
Five per cent if the job is formed up tight on a level, well compacted base, 10 per cent for a normal job, and 15 per cent on soft or uneven subgrade where the concrete will find every low spot. Never order dead level with the calculation. Running short mid pour creates a cold joint, which is a permanent weak line through the slab, and it cannot be fixed afterwards.
What is the sizing mistake that costs the most in Rockhampton?
Getting the depth wrong rather than the area. A base that sits 30mm low across a 60 square metre slab swallows an extra 1.8 cubic metres of concrete, which is $540 to $720 you did not budget for, and you find out about it when the last truck runs out. Dig three test holes across the pad and check the depth against a string line before you order, because area is easy to measure and depth is the one people guess.
How many sheets of mesh do I need for a slab?
A standard SL72 sheet is 6m by 2.4m, which is 14.4 square metres, but once you lap the sheets you get about 13 square metres of coverage from each one. So allow one sheet per 13 square metres and round up: a 54 square metre shed slab takes 5 sheets. SL72 runs about $95 to $140 a sheet in 2026 and SL82 about $130 to $190, plus roughly 4 bar chairs per square metre to hold it up.
Is it cheaper to use bagged concrete for a small job?
Only for very small pours. A 20kg bag of premix yields about 0.01 cubic metres, so a cubic metre takes roughly 100 bags, and at $9 to $13 a bag that is $900 to $1,300 against $300 to $400 for delivered mix. Bags win under about 0.3 cubic metres, which is a clothesline footing or a small step, because at that size a truck delivery attracts a short load fee of $100 to $300 anyway.
How much road base goes under a Rockhampton slab?
Allow 100mm of compacted road base as a minimum on stable ground and 150mm to 200mm on reactive clay. Road base loses roughly 20 to 25 per cent of its volume when it is compacted, so for 100mm finished under a 54 square metre slab you order about 7 cubic metres loose to end up with 5.4 compacted. Delivered in the Rockhampton region that is around $60 to $110 per cubic metre for a small load.
Get a price

Have us measure it and quote the finished slab

Send your rough sizes and we will come out, measure properly, and email a fixed written quote with the volume, the steel and the finish itemised, usually within a few days.

We reply within 1 business day. Free, no obligation.

Got the numbers but not the crew?

We pour house slabs, shed slabs, driveways and paths across Rockhampton, North Rockhampton, Gracemere, Yeppoon, Parkhurst and Mount Morgan, and the measure is free.

 Tap to call