Concreting a new build in Rockhampton.

Handover day, brand new house, and a dirt driveway. It catches almost every first-time builder, because the concrete you assumed was included mostly is not. Here is what a new home actually needs, why filled estate blocks make people wait, and what the whole lot costs.

The gap

What the builder leaves out.

Because most volume builders in Central Queensland include only a minimal path and sometimes a short apron, and leave the driveway to you or price it as an expensive upgrade. It is not a scam, it is how the base price is kept competitive. What it means practically is that on handover day you own a house with no way to drive onto it. Read your inclusions list for the words path, apron, driveway and crossover, and find out exactly where the builder’s concrete stops. That boundary is your bill.

And the list is longer than the driveway. More than people budget for. The driveway and the council crossover, a path to the front door, a path down the side to the meter and bins, a clothesline or drying pad, an air-conditioner condenser pad, a patio or alfresco slab if it was not in the contract, and a shed slab if a shed is coming. On a typical Parkhurst or Gracemere block that adds up to 70 to 110 square metres of concrete beyond the house slab, which is real money that most first-time builders do not have in their number.

The estate trap

Filled blocks need to settle. Really.

On a filled block, yes, and this is the single most important thing on this page. New estates around Rockhampton are cut and filled to create level lots, and engineered fill keeps settling for a while after it is placed. Pour a driveway over fresh fill and it will follow the ground down. Where fill is deep or recent, waiting six to twelve months through at least one wet season lets it settle. Ask the developer or your builder for the fill depth and the compaction test results, and if the answer is vague, wait.

Here is why this is worse in Rockhampton than in most places. Your house slab was engineered for the site classification under AS 2870, so it was designed to sit on that fill and it will be fine. Your driveway was not engineered for anything, because driveways rarely are. So on a block where the house is on 1.2 metres of fill down the low side, the house stays put and the driveway drops. The crack always turns up in the same place, right where the fill depth changes, which is the mechanism explained in concrete cracks: when to worry.

What we do about it: we ask for the fill plan before we quote. On shallow or old fill we pour. On deep or recent fill we will either tell you to wait, or price a thicker slab with heavier mesh and more joints that can tolerate some movement. What we will not do is pour 110 dollars a square metre onto ground we know is still moving and hand you a warranty that means nothing. Ground behaviour on this soil is covered in slab prep on reactive soil.

Timing

Book earlier than feels necessary.

Two moments, and they are months apart. The house slab is booked by your builder as part of the contract, so you have little say in it. The concreting you do control is everything after handover: the driveway, the paths, the shed slab, the patio and the clothesline pad. Book that as soon as you have a realistic handover date, because the dry season book fills months ahead and every other new owner in your estate wants the same weeks. Getting the quote done before handover costs nothing and saves you sitting on a dirt driveway until September.

The estate effect is real and people underestimate it. When forty houses in one release hit handover within the same quarter, forty owners ring for a driveway in the same fortnight, and they all want it in June. Ring in February with a June handover and you get June. Ring in June and you get spring. The seasonal argument is in the best time of year to pour.

One piece of paperwork to start early: the crossover. The section from the kerb to your boundary sits in the road reserve and needs a vehicle crossing permit from Rockhampton Regional Council, or Livingstone Shire Council if you are at Yeppoon or on the Capricorn Coast. It is not hard, it just takes time you will not want to spend when the truck is booked. Details in do I need council approval.

The saving

Do it in one hit.

Often yes, and it is the easiest saving available. Every separate visit carries its own set-up, formwork mobilisation and minimum truck load, so three small jobs across three months cost noticeably more than the same area done in one hit. Doing the driveway, paths and patio together on one day can save several hundred dollars and gives a better colour match, because it is all from the same batch. The exception is anything sitting on deep new fill that genuinely should wait, and a shed slab that cannot be set out until the shed is ordered.

The colour-match point is underrated. Concrete poured six months apart from different batches will never be the same shade, and on a front driveway meeting a front path that difference is visible forever. If the two are going to touch and both will be seen, pour them together or accept the line.

The money

What a new build actually costs in concrete.

2026 rates for the post-handover work: plain slab or path on stable ground $90 to $130 per m², exposed aggregate $130 to $200 per m², coloured or stencil $120 to $190 per m², and a shed slab with a thickened edge $110 to $160 per m². A concrete pump is $650 to $1,500 where the truck cannot reach, which on a narrow new-estate block with the landscaping already in happens more than you would think.

A worked example, a typical Parkhurst new-estate block on shallow fill. Driveway 42m² in exposed aggregate at $160 per m² is $6,720. Front path 12m² in aggregate to match, $1,920. Side path to the bins 14m² plain broom at $110, $1,540. Alfresco slab 20m² plain at $115, $2,300. Clothesline and condenser pads, $450. Crossover permit and the crossing itself, about $1,300. All poured on two days rather than five separate visits. Total roughly $14,230.

Then the shed, when it comes: a 6m by 9m shed slab on this ground with an engineered edge beam, soil test, engineering and certifier is around $12,900 all in. Which is why we tell people to get the shed slab quoted at the same time as the driveway even if the shed is two years away. It changes where you run the driveway. Full rates on the cost guide, and how to choose a concreter covers what to check in each quote.

Where we work

New estates across the region.

Parkhurst Gracemere North Rockhampton Yeppoon Mount Morgan All service areas Norman Gardens Frenchville Kawana Rockyview Glenlee Berserker Park Avenue Zilzie Emu Park Taranganba

New build questions.

When should I book the concreter on a new build in Rockhampton?

Two moments, and they are months apart. The house slab is booked by your builder as part of the contract, so you have little say in it. The concreting you do control is everything after handover: the driveway, the paths, the shed slab, the patio and the clothesline pad. Book that as soon as you have a realistic handover date, because the dry season book fills months ahead and every other new owner in your estate wants the same weeks. Getting the quote done before handover costs nothing and saves you sitting on a dirt driveway until September.

Why is the driveway not included in my new house contract?

Because most volume builders in Central Queensland include only a minimal path and sometimes a short apron, and leave the driveway to you or price it as an expensive upgrade. It is not a scam, it is how the base price is kept competitive. What it means practically is that on handover day you own a house with no way to drive onto it. Read your inclusions list for the words path, apron, driveway and crossover, and find out exactly where the builder’s concrete stops. That boundary is your bill.

Should I wait before pouring a driveway on a new-estate block?

On a filled block, yes, and this is the single most important thing on this page. New estates around Rockhampton are cut and filled to create level lots, and engineered fill keeps settling for a while after it is placed. Pour a driveway over fresh fill and it will follow the ground down. Where fill is deep or recent, waiting six to twelve months through at least one wet season lets it settle. Ask the developer or your builder for the fill depth and the compaction test results, and if the answer is vague, wait.

What concreting does a new home actually need beyond the slab?

More than people budget for. The driveway and the council crossover, a path to the front door, a path down the side to the meter and bins, a clothesline or drying pad, an air-conditioner condenser pad, a patio or alfresco slab if it was not in the contract, and a shed slab if a shed is coming. On a typical Parkhurst or Gracemere block that adds up to 70 to 110 square metres of concrete beyond the house slab, which is real money that most first-time builders do not have in their number.

Can I do all the new-build concreting in one pour to save money?

Often yes, and it is the easiest saving available. Every separate visit carries its own set-up, formwork mobilisation and minimum truck load, so three small jobs across three months cost noticeably more than the same area done in one hit. Doing the driveway, paths and patio together on one day can save several hundred dollars and gives a better colour match, because it is all from the same batch. The exception is anything sitting on deep new fill that genuinely should wait, and a shed slab that cannot be set out until the shed is ordered.